Page 90 - 香港房屋協會 Hong Kong Housing Society Annual Report 2020/2021
P. 90
88
HONG KONG HOUSING SOCIETY ANNUAL REPORT 2020/21
DEDICATED REHOUSING ESTATES
From 2018, in tandem with Government’s initiative to introduce a non-means-tested rehousing option for eligible households as part of the enhancement to the general compensation and rehousing arrangements for Government’s development clearances, the Housing Society has four Dedicated Rehousing Estates (DRE) down the pipeline to provide such non-means- tested rehousing arrangement. These DREs are all located in newly developed areas.
Pak Wo Road, Fanling
For the site on Pak Wo Road in Fanling, foundation works are nearly completed and superstructure works are expected to commence in mid-2021. The project will provide around 1,460 rental, SSF and SEN units, plus two residential care homes for the elderly, a shopping centre and public car parking spaces. It is scheduled for completion in 2024.
Hung Shui Kiu Phase I
The Government invited the Housing Society to develop the DRE at Hung Shui Kiu in Yuen Long, for which a three-phase planning and construction programme is underway. Phase IA comprises a 27-storey tower with 300 SSF units built with Modular Integrated Construction (MiC) in concrete module whereas Phase IB will be developed into a 32-storey tower with about 370 rental units. Foundation works for both phases had already commenced and both developments are expected to be completed by end 2024. Phase II and III works will commence in 2022 and 2026.
The entire Hung Shui Kiu DRE project is scheduled for completion by 2029, providing around 2,580 flats, including rental and SSF units.
Pak Wo Road project
粉嶺百和路項目
專用安置屋邨
自二零一八年,為配合作為政府發展清拆行 動的一般補償及安置安排之一,政府為合資 格住戶推出豁免入息審查的安置項目,房協 有四個專用安置屋邨項目在籌備中,以提供 該等豁免入息審查的安置房屋。該等專用安 置屋邨均位於新發展區。
粉嶺百和路
粉嶺百和路項目的地基工程將近完工,而預 期上蓋工程將於二零二一年中動工。項目將 提供約一千四百六十個出租、資助出售房屋 和「長者安居樂」單位,另配備兩間護理安老 院舍、一個購物中心及公眾停車場。預計項 目於二零二四年落成。
洪水橋第一期
政府邀請房協發展元朗洪水橋專用安置屋 邨,並正進行分三期規劃和施工的項目計 劃。項目的第IA期包括利用混凝土「組裝合 成」建築法興建一幢二十七層高的大廈,提供 三百個資助出售房屋單位,而第IB期將發展成 一幢三十二層高的大廈,提供約三百七十個 出租單位。兩期地基工程均已展開,而預期 兩期發展項目將於二零二四年底完成。其餘 第二及三期將於二零二二及二零二六年動工。
預計整個洪水橋專用安置屋邨項目將於二零 二九年落成,提供約二千五百八十個單位, 包括出租和資助出售房屋單位。
Hung Shui Kiu Phase 1A project 洪水橋第 1A 項目